HomeMy WebLinkAboutBDI/BRPH Task Order Main WWTP Bldg. Renovation 7-18-13 TASK ORDER CITY OF CAPE CANAVERAL MAIN WASTEWATER TREATMENT PLANT BUILDING RENOVATION ARCHITECTURAL AND ENGINEERING SERVICES Section I. BACKGROUND The City of Cape Canaveral has an existing main building located at the Wastewater Treatment Plant site. This Task Order will allow the BDI/BRPH Team to provide the architectural and } engineering services for the renovation of this building. Section II. SCOPE OF SERVICES The BDI/BRPH Team will provide Architectural, Mechanical, Electrical, Plumbing, and Structural design services as outlined below for the following renovation to the main WWTP building. • Remodel of the existing laboratory, limited to; doors, windows, lighting, wall finish, ceiling, and fecal/autoclave location adjustments • Complete remodel and expansion of the existing break room into a multipurpose room (break/training/conference) • Remodel of the existing bay area, limited to; doors, windows, lighting, wall/ceiling/floor finish, and removal of unused electrical equipment • New male and female locker rooms within the bay area • New elevated operator control room within the bay area • New hot water tank and washbasin within the bay area • New fecal area near the lab within the bay area • New chlorine tank storage building extension on the east side of the existing building, excluding tank, new piping, and chlorine equipment relocation. • New exterior finish of the existing building DESIGN/DRAWINGS The BDI/BRPH Team will prepare final construction documents ready for bid consisting of Architectural, Mechanical, Electrical, Structural and Plumbing drawings and specifications. • Architectural design plans and specifications including floor plans, elevations, details and life safety plans. • Interior Design and Finish Plans • Architectural, electrical, mechanical, structural and plumbing design, including power, lighting, and fire alarm design. • Complete structural plans indicating foundation and superstructure. The BDI/BRPH Team will provide Design Submittals and conduct review meetings at the 50% and 100% phases of design, and provide one set of responses for each phase. PERMITTING The BDI/BRPH Team will assist with obtaining the required City building permit. Preparation of a response to one (1) Request for Additional Information (RAI) from the Building Official is included in this Task Order. Additional responses will be in accordance with corporate hourly rates. BIDDING AND NEGOTIATION SERVICES: The BDI/BRPH Team will perform the following services during the bidding process: • Preparation and assembly of construction bid documents, including; plans, specifications, and contract documents. • Preparation and distribution of addenda as may be required during the bidding and negotiation process. • Participate in a pre-bid conference. • Field bidder questions and provide responses to those questions, along with any necessary clarification/interpretation of the bid documents. • Evaluate submitted bid packages. • Provide a recommendation of award. CONSTRUCTION SERVICES: The BDI/BRPH Team will perform the following services during the construction period: • Attend ten (10) periodic meetings during construction. • Review required submittals, shop drawings, and samples for work under our design. • Answer formal Requests for Information (RFI's) prepared by the Contractor. • Prepare and issue Architect's Supplemental Instructions (ASI's) when appropriate to incorporate modifications or clarifications. • Perform a Substantial Completion inspection and issue a punch list (PL) of items to be completed for Final Completion. • Perform a Final Completion inspection. • Draft final record drawings from Contractor red-lines for project closeout requirements. • Provide electronic version of record drawings. EXCLUSION The following work is not included in this Task Order, but can be performed as additional services: • Roof replacement is not included (except for the existing chlorine area roof, which is included) • No work is scheduled for the Sludge Holding, CCC, and Filtration & Effluent transfer pumps. 2 Section III. SUBCONSULTANTS BRPH will serve as a subconsultant to BDI providing architectural services for this project. • Section IV. OWNER'S RESPONSIBILITY The City of Cape Canaveral will provide all available design related information on the existing Main WWTP building. The City will review and provide one set of comments each on the 50% and 100% design documentation. The City will work in conjunction with the Architect-Engineer Team to assist with construction observation. The City will be responsible for all permit fees. Section V. DELIVERABLES The BDI/BRPH Team will provide the following deliverables to the City of Cape Canaveral: 1. Three (3) sets of the 50% Plans and Cost Estimate. 2. Three (3) sets of the 100% Plans, Specs and Cost Estimate. 3. Three (3) sets of signed and sealed final construction documents for permitting. 4. One (1) Electronic copy of the Final 100% Contract Documents in PDF format. Section VII. SCHEDULE BDI/BRPH Team project schedule is as follows: Task Schedule Receive City approval 7/16/13 Design Team — Program Validation & Kick-Off 7/19/13 Prepare floor plans 2 weeks Present floor plans Revise floor plans (if necessary) 1 week Receive Client approval of floor plans & design Prepare 50%construction documents 4 weeks Receive Client comments & approval of 50% CD's 1 week Prepare 100%construction documents 4 weeks Receive Client comments & approval of 100% CD's 1 week Final construction documents 1 week Final submittal Bidding / Permitting: 4 weeks Construction contractor approval Start Construction: 6 to 7 months Substantial completion 6/13/14 3 1 Section VIII. METHOD OF COMPENSATION The City of Cape Canaveral shall compensate the BDI/BRPH Team for the not-to-exceed lump sum fee amount as listed below for a total value of One Hundred Twenty Three Thousand One Hundred and Fifty-five Dollars and Zero Cents ($123,155) for the scope of services as specified prior in this task order. The cost breakdown for this project is as follows: Task Total Develop Existing Drawings $ 10,245 Structural Analysis $ 6,565 Design Development (50%) $ 11,769 Construction Documents (100%) $ 68,818 Construction Admin $ 25,758 Totals $ 123,155 The fixed costs listed above include the following expenses: plotting and reproduction for in- house design purposes;three sets of black line drawings for owner review at each design milestone; and three sets of signed and sealed final construction documents for permitting. SECTION IX. ACCEPTANCE If the above scope and fees meet your approval, please indicate by your signature in the space provided below and return one (1) signed copy which will constitute an "Agreement and Notice to Proceed"for the accomplishment of this work. BASKERVILLE-DONOVAN, INC. CITY OF CAPE CANAVERAL IA/ Oai-44 } Keith Hil P.E. EV P/CO e June 12, 2013 74'Q/13 Date to 4