Loading...
HomeMy WebLinkAboutTask Order Facility Planning Services 8-28-12TASK ORDER CITY OF CAPE CANAVERAL WASTEWATER AND STORMWATER IMPROVEMENTS PROJECT FACILITY PLANNING SERVICES Section I. BACKGROUND The City of Cape Canaveral is in the midst of important improvements to the City's existing wastewater and stormwater systems. To support these improvements, the City Staff has identified the use of the very cost-effective funding source, the low-interest FDEP State Revolving Fund (SRF) Loan Program. To assist the City of Cape Canaveral with the SRF Facility Planning Services, the City has selected the professional consulting services of Baskerville -Donovan, Inc. (BDI). This Task Order will allow the BDI Team to provide the SRF Facility Planning Services for these important wastewater and stormwater system projects. Section II. SCOPE OF SERVICES - Planning Services TASK 1 — SRF FUNDING ASSISTANCE The BDI Team will provide the City of Cape Canaveral with Wastewater and Stormwater System State Revolving Fund (SRF) Program funding assistance through the preparation of the SRF Facility Planning documentation. The City will need to complete SRF Facilities Planning documentation plus other SRF services to be able to attain the SRF low—interest funding source. The BDI Team will be responsible for the preparation of a single Wastewater and Stormwater System State Revolving Fund (SRF) Program facility planning document. The City of Cape Canaveral/BDI Team has identified the following list of ten (10) wastewater and stormwater projects to be included in the FDEP SRF Loan Program Facility Planning process. City of Cape Canaveral Wastewater and Stormwater Proiects The City of Cape Canaveral specific Wastewater and Stormwater Projects are as follows: 1) WWTP Oxidation Ditch Improvements 2) WWTP Belt Filter Press Improvements 3) 3MG Reclaimed Water Storage Tank and Pump Station 4) Culvert for North Central Ditch - Phase 1 5) Culvert for North Central Ditch - Phase II 6) North Atlantic Ave Streetscape Stormwater Portion 7) West Central Pipe Replacement 8) Central Ditch Dredging 9) Canaveral City Park Stormwater Exfiltration System at Park 10) Holman Rd Sanitary Sewer System (2000 LF Pipe Replaced) 1.1 SRF Project Facility Planning Services The BDI Team will provide the City of Cape Canaveral with project planning services that will allow the City to use the FDEP SRF Clean Water Program. These services will include the preparation of a Water Facilities Plan as required by the FDEP BWFF, provide an Engineer's opinion of probable construction cost info for the capital finance plan, assist at the public hearing, and coordination with the City, the FDEP BWFF, the Berryhill Group, and Raftelis Financial Consultants related to the SRF Program Requirements. The specific activities to be completed are provided as follows: [ 5 3r,.G ., _. yi'.. ;31 _ .., i _ .,. d\a. ,,..-., .✓',r?' y `'35':T .. _. 1) Preparation of the City's 20 -Year Wastewater & Stormwater Facilities Plan including the following tasks: o Collect and compile data on Wastewater/Stormwater projects and City existing planning docs o Field Visits to some Project Sites o Facility Planning Service Area, Population, and Flow Projections o Development of Wastewater/Stormwater Project Concepts and Alternatives (10 Projects) o Evaluation of Projects and Alternatives .(10 Projects) o Engineer's Opinion of Probable Construction Costs o Preferred Wastewater/Stormwater Projects (10 Projects) o Draft Wastewater/Stormwater Facilities Plan o Coordination & Cost Information for Draft Capital Financing Plan (w/Raftelis) o Assistance for Public Hearing Approvals o Environmental Clearance Process Assistance (FONSI) to Expedite o Coordination w/City, FDEP BWFF, Berryhill Group on SRF Requirements o Review Facility Plan with Client Meeting (1) o Final Wastewater/Stormwater Facilities Plan 2) Assist at the SRF Program Public Hearing 3) Coordinate with the City, FDEP BWFF, the Berryhill Group, and Raftelis Financial Consultants on SRF Program Requirements Section III. SUBCONSULTANTS The BDI Team will include the subconsultant services of Infrastructure Solution Services for this task order. BDI will coordinate with the City's direct subconsultants, The Berryhill Group & Raftelis Financial Consultants. Section IV. PERMITTING No permits will be required on this planning task order. Section V. OWNER'S RESPONSIBILITY The City of Cape Canaveral will provide all planning documentation, related design documents, and City guidance documentation required to prepare this SRF Facility Plan. The City will provide specifics on the projects that are desired to be added to the Facility Planning documentation. The City will review and provide comments on the draft Facility Plan documentation. The City will direct hire the subconsultants, The Berryhill Group & Raftelis Financial Consultants. Section VI. DELIVERABLES The BDI Team will provide the following deliverables to the City of Cape Canaveral: 1. Three (3) copies of the draft Wastewater/Stormwater Facilities Plan 2. Ten (10) copies of final Wastewater/Stormwater Facilities Plan 3. One (1) Electronic copy of the final Facilities Plan in PDF format. Section VII. SCHEDULE BDI Team project schedule was developed based on similar Facilities Planning work completed by the BDI Team. TASK NAME TASK DAYS CUMUL DAYS Draft Facilities Plan 60 60 Owner Review & BDI QC Review 10 70 Final Facilities Plan 20 90 Total Project Duration 90 Section VIII. METHOD OF COMPENSATION The City of Cape Canaveral shall compensate the BDI Team for the Facility Planning Scope of Services as specified prior in this task order for a lump sum fee amount of Seventy One Thousand Nine Hundred and Eighty Dollars and Zero Cents ($71,980.00). At the direction of the City of Cape Canaveral and BDI Agreement, BDI may be requested to provide additional services including but not limited to special studies, such as GIS services, surveying services, etc. These additional services would be requested and approved by the City of Cape Canaveral. BDI shall invoice the City of Cape Canaveral monthly based on the percentage of work actually completed on this project. Section IX. ACCEPTANCE If the above scope and fees meet your approval, please indicate by your signature in the space provided below and return one (1) signed copy which will constitute an "Agreement and Notice to Proceed" for the accomplishment of this work. BASKERVILLE-DONOVAN, INC. Thomas Vill, P.E. Regional Manager, V.P. 26.22-/- Date CITY OF CAPE CANAVERAL c9u..� `L t -f �+cc�•e� x/2.§1" Date Q W 2 0 w IL 0 z_ Z Z Q J IL J_ V Q U. 3 v O cc a` 0 C N E 0 C z C6 Q a r W Q LL L LU L5 r U) E 3 N Q ca � a LU z UNIM C� C C O 111 V c ma N li c U m O w a L 06 U H V c O O C a� c a w n c m CL m '00 N v O Q H N N m m N N m C4O 10 COD 8 N N NNH O N W N N 2 � O F W Z 2 O N E a m In Okco o d mgm m hco to CD ar m Ci z 0 Z N -j 00 F u9 L 0 47 cN G 0 CO O O O c' U � N N J Q � N c O Y m m O m w O O O O Vi Z m r z W Z to m fA n � H C o m o i c O O O fA 'CooC a m o U cav IU) = m N cc 0 069 E m n w 'c � U o� (N'J N N n N m _ cc w m m N C', 0 C11 GoOD m =N c c 0 O N d 0 m N ri co N m Q aN Cl) c d d m m N m d a d d d m 69 w a N O o0 � of N _ c= w d d d m N d m m d d N d d m N 69 m` m m O oco m ar d d d 'O d d d 0 w O 10 N n rA a m 2 W x x LL c m 000 L o d QQ J J J cm o J J J N U) f 0 O QI 1 Z E O O _ c d m 0 E U. 13 m Q t0 c c c ty U 41 N co O 2 Q m 0 N 0 m 5 E d LL m¢ O.d U y O _ C U3 m 3 O y C O E O LL '0m U oo m U o o c d oa �j R0 a o v, ca c =_ m Z: o ffi� �a o EL a °mc>om d 3 3 a=_19o-mm V LU a o 1O 0 0 0 wLL� m V CE y m 3lL UQ 03 CLL m m m m m oEo LU m¢ m-om o;-° LLaU; mm �n.0 m m min $ E Ea=3C3 o c m LL 3 0 im �m bo wm[n "c,"a ct0 i z o� 3� w m m c a p v a m W E .K C C a C O d O in C7 LL LL 3 id a J000'c o ��Uro3_oocp mo�y3mLDmmo�D3 3 nm Es3'om.�c2n+LLm 2 oma, Y UES- o`° �3UVma 33 O G m O p -O = m N N C) U > O m ,� d ,� m vai a W O .m �d m C x W H �LLLLow0aoo¢¢USLL c m CL N NNH O N W N N 2 J IL W Z 2 O mgm N Z N -j 00 F Z W 0 CO N N J Q 0 c O Y m m w z W Z H C o i c 0 o U cav IU) N c m CL v W 7 0 cc a C7 z z z a J a _J v a LL P z W W 0 m IL 2 J a W a z a U W a a LL 0 H LE N m a roi a o M n N 09 O O M N co N of ' 1� 0 H H Hl H!H Wk NlHNus. NHH Leri Oou� oo�n�noi o 0 U 0 coc m V Lo CS � o O Lo N HH to NNHNHN N mE L U _N U U U U ms E c m ya mm `m L J m aaaaa d d a N � r = o 0 to 4 W fqW ZWZ a x a W W W W Q m O J Z � fAZW J H C U) N O M 3 f9 0 O it m N m �� ° X x�� M m C m Q X K _m $30 oU Vjm'RSN X app W m m o3;00 CL w a E 0 m ° •- r _m m m o m U U Z_ c mq o mm m- m Z W NfA fA¢ a C j2CL O `m — Q W W W W d m rn aaaa� n ` F UUUUUmw ?e N m a