HomeMy WebLinkAboutChangeOrder#5 MEMORANDUM
TO: Ryan Herold
Brewer Paving and Development, Inc.
FROM: Jeff Ratliff
Assistant Public Works Director
City of Cape Canaveral
868 -1240
DATE: 01/19/11
RE: Change Order No. 5
Ridgewood Avenue Improvements Project
Change Order No. 5 was approved by the City Council on January 18, 2011 and included
additional funds in the amount of $58,194A9 for performing additional construction
tasks. These tasks included the construction of a poured concrete wall, milling/paving of
° a parking lot, etc. If in agreement, please sign below and return the original to the City.
d2M/
Walter Bandish Billy Joe Brewer
Public Works Director President
City of Cape Canaveral Brewer Paving and Development, Inc.
j
{
Ridgewood Project Tracking
Request for Additional Survey_ Work SSA
Additional Survey Work Needed - Estimated 1 1 1 LS $ 7,415.00 $ 7,415.00
Subtotal _ $ 7,415.00
Additional Driveways - Not Shown on Plans
Removal of Ex Concrete - 7925 34 SY $ 5.00 $ 170.00
6" Concrete for Driveways - 7926 34 SY $ 28.00 $ 952.00
Removal of Ex Concrete - 7923 37 SY $ 5.00 $ 186.00
6" Concrete for Driveways - 7923 37 SY $ 28.00 $ 1,036.00
Removal of Ex Concrete - 7921 28 SY $ 5.00 $ 140.00
6" Concrete for Driveways - 7921 28 SY $ 28.00 $ 784.00
Removal of Ex Concrete - Jaokson & Harrison West Side 27 SY $ 5.00 $ 135.00
ti 6" Concrete for Driveways - Jackson & Harrison West Side 27 SY $ 28.00 $ 756.00
Subtotal $ 4,168.00
Additional Roadway Work at NW Corner of Monroe - Existing had negative flow
Removal of Asphalt 9 SY $ 5.00 $ 45.00
8" Stabilized Subgrade 9 SY $ 3.38 $ 30.42
8" Base Course 9 SY $ 9.00 $ 81.00
Asphalt 1 TN $ 90.00 $ 90.00
Subtotal $ 248.42
Removed Asphalt No Parking Areas at Morgan Manor Placed dirt and Graded
Removal of Asphalt 110 SY $ 5.00 $ 550.00
Install Fill Dirt for Grading (2" - 4 ") 110 SY $ 4.00 $ 440.00
Grading of Area 110 SY $ 2.75 $ 302.50
Subtotal $ 1,292.50
Extra Concrete Driveway - Fill Green Areas Between Harrison & Tyler
Concrete Driveway Turnout 19 SY $ 28.00 $ 532.00
Credit for Fill at Green Areas -3 CY $ 2.00 $ (6.00)
Subtotal $ 526.00
4' Asphalt Strip i NW Corner of Harrison from Driveway Tie-In to Light Pole (4' x 62')
Excavate for Subgrade 28 SY $ 2.75 $ 77.00
8" Stabilized Subgrade 28 SY $ 3.38 $ 94.64
6" Base Course 28 SY $ 9.00 $ 252.00
Asphalt 2.5 TN $ 90.00 $ 225.00
Subtotal $ 648.64
Install Yard Drain & Piping
Install Yard Drain & Piping 1 2 1 EA $ 750.00 $ 1,500.00
Subtotal _ $ 1,500.00
Relocate Trees
Relocate Trees 1 5 1 EA $ 150.00 $ 750.00
Subtotal $ 750.00
Remove Sidewalk Panels for Sidewalk Tie -Ins
Remove Sidewalk - Buchanan 6 SY $ 5.00 $ 30.00
Replace Sidewalk - Buchanan 6 SY $ 28.00 $ 168.00
Remove Sidewalk - Lincoln 3 SY $ 5.00 $ 15.00
Replace Sidewalk - Lincoln 3 SY $ 28.00 $ 84.00
Remove Sidewalk - Pierce 4 SY $ 5.00 $ 20.00
Replace Sidewalk - Pierce 4 SY $ 28.00 $ 112.00
Subtotal $ 429.00
Costa Del Mar
Maintenance of Traffic 1.00 LS $ 250.00 $ 250.00
Excavation & Embankment 1.00 LS $ 750.00 $ 750.00
,
$$g 1
Remove Existing Asphalt & Base 271.00 SY $ 5.00 $ 1,355.00
. Finish Grading 1.00 LS $ . 500.00 $ 500.00
8" Stabilized Subgrade 271.00 SY $ 3.38 $ 915.98
6" Base Rock 271.00 SY $ 9.00 $ 2,439.00
Prime 271.00 SY $ 0.45 $ 121.95
1 1/2" SP 9.5 Asphalt 25.00 TN $ 105.00 $ 2,625.00
Striping 1.00 LS $ 900.00 $ 900.00
Subtotal $ 9,856.93
6920 Ridgewood Avenue
Remove Existing Concrete Block Wail 205.00 LF $ 25.00 $ 5,125.00
Install New Concrete Block Wall 169,00 LF $ 80.00 $ 13,520.00
Additional 4" Thick Concrete Sidewalk 10.00 SY $ 23.50 $ 235.00
Finish Grading of Property 1.00 LS $ 1,500,00 $ 1,500.00
Sodding of Disturbed Yard - 5' Wide - No irrigation 94.00 SY $ 3.00 $ 282,00
Subtotal $ 20,662.00
Irrigation
Washington to Monroe Avenues /Cherie Down Residents 1.00 LS $ 2,626.00 $ 2,625.00
Landscape Additions (09/25/10) 1.00 LS $ 1722.50 $ 5,722.50
Irrigation Additions to Taylor Avenue 1.00 is $ 2,362.50 $ 2,362.50
Subtotal $ 10,710.00
Total Extras To -Date $ 58,194.49
}