HomeMy WebLinkAboutMinutes 01-09-1991 CAPE CANAVERAL
PLANNING & ZONING BOARD
REGULAR MEETING
JANUARY 9 , 1991
A Regular Meeting of the Planning & Zoning Board of the City of
Cape Canaveral , Florida , was held on January 9 , 1991 at the City
Hall Annex, 111 Polk Avenue , Cape Canaveral , Florida. The meeting
was called to order at 7 : 30 P .M. by Chairman Russell . The
Secretary called the roll .
MEMBERS PRESENT
Lamar Russell Chairman
Arthur Berger Vice Chairman
Richard Thurm
Mary Wheeler
Wayne Washburn
Cecil Everett Alternate
OTHERS PRESENT
Edward Spenik City Manager
Kohn Bennett Deputy City Attorney
Thomas Kleving Building Inspector
Evelyn Hutcherson Code Enforcement Officer
Susan Nelson Secretary
Mr . Everett amended the minutes to read as follows : Mr. Everett
stated in discussion item No. 1 , that it was his opinion that the
RPUD Ordinance be put to a test to see what the outcome would be .
Mr . Thurm moved to approve the minutes of December 12 , 1990 as
amended. Ms . Wheeler seconded the motion. Motion carried
unanimously.
NEW BUSINESS
1 . Variance Request No. 91-1 to Construct Canopy over existing
Dispensing Islands , (Highway Oil , Inc. , 8090 Astronaut Blvd. )
Parcel 259 , Sec . 23 , Twp. 24S , Rge. 37E - C. S . Tate for Tom
G. Platis , President
Mr. Tate , representative for Highway Oil , Inc . , explained that a
canopy and islands were removed in order to remove and replace the
underground tanks because the underground tanks did not comply with
EPA State codes . He pointed out that other stations in the general
area had canopies that did not meet the current setback
requirements and that the closest portion of the canopy for Highway
Oil would be approximately 13 feet into the setback. Mr . Tate
stated that if the variance was not granted, it would impose a
hardship to the business because of inconvenience to customers due
to undesirable lighting and bad weather. He noted that the
Building Department had approved the footer to anchor the canopy
and that the footers had already been installed. The Board members
reviewed photos of the canopy footers .
Mr . Kleving, Building Inspector, commented that the applicant had
applied for a building permit to install the footers and canopy.
However, the application was turned down and no inspection was made
of the footers because it was the Building Official ' s opinion that
an inspection would be a tacit approval for the permit on erection
of the canopy. The applicant had been instructed by the Building
Official to have engineering approval on the footers and canopy
drawing. Mr. Tate reiterated that the footers had engineering
approval and certification.
Planning & Zoning
Regular Meeting
January 9 , 1991
Page 1 of 2
0
Mr. Kleving noted that it was the Building Official ' s
interpretation that the canopy would encroach into the setback and
would require a variance.
The Board members reviewed photos of the proposed canopy and also
existing canopies on stations in the general area. Mr. Berger
commended the Building Department staff for taking photos and
measurements of existing canopies in service stations in the area.
Discussion followed.
It was determined that since the structure was more than 50%
destroyed, the replacement of the canopy had to comply with current
regulations .
Mr. Kleving and Ms . Hutcherson , Code Enforcement Officers , could
not foresee any definable safety hazards if the variance was
granted. It was Ms . Wheeler ' s opinion that the canopy would
enhance the neighborhood and service station.
The Board members reviewed the Zoning Regulations , Sections 641 . 23 ,
Accessory Structures ; 643 . 05 , Non-Conforming Structures ; 643 . 07 (B) ,
Non-Conforming Uses of Structures ; and 641 . 21 (E) Setback
Encroachments . Discussion followed.
It was the consensus of the Board members that the pumps and canopy
were removed as a result of complying with EPA regulations to
replace underground tanks ; that a hardship existed which was not
self-imposed; and that it was an irregular piece of property not
easily usable for anything.
Mr. Thurm moved to recommend approval of Variance Request No.
91-1 to the Board of Adjustment . Ms . Wheeler seconded the motion.
Motion carried unanimously.
There being no further business , the meeting was adjourned at 8 : 05
P.M.
Approved this /.3 T74 day of 4-0-- {GA . 1991 .
X? AdAt-ei
Chairman
7.Thwov,r1 L , /U2iL 01-1
Secretary
Planning & Zoning
Regular Meeting
January 9 , 1991
Page 2 of 2